Welcome to the North Valleys Improvement projects site. This is will have the most current updates from RTC Washoe, NDOT and Washoe County that will impact the North Valleys.

Project Timelines

rtcwashoe.com/engineering-project/golden-valley-road-rehabilitation/(opens in a new tab)

2019-2020

Reconstruction from North Hills Boulevard from Lemmon Drive to Golden Valley Road

COMPLETED

2019-2020
2020

After removing the bridge, it is anticipated the contractor will open the new bridge and ramps to the public within 4 months. It is estimated the actual bridge replacement construction will take four months. The actual construction project duration is seven to eight months. Once a contractor is awarded, we will share a more detailed construction schedule affecting the bridge and freeway ramps.

2020
2020

Design and construction of a new force-main. The new forcemain will be constructed from
the Golden Valley Lift Station, run west to Virginia Street,
and then run south to terminate at the existing gravity line
at Security Circle.

2020
2021

Widening Lemmon Drive from US 395 to Military Road from four lanes to six lanes

2021
2021

Project will be Rehabilitation/Widening of Sky Vista Parkway, new sidewalks both side of the roadway, curb/gutter, signal work/roundabout, bike lanes both sides of the roadway, improved bus stops.

2021
Near Term

Widening Lemmon Drive from Fleetwood Drive to Chickadee Drive from two lanes to four lanes

Near Term